To:            Headteacher

All Schools

 

 

Dear Headteacher

 

NATIONAL GRID FOR LEARNING (NGFL) PHASE 5 PROGRESS

 

As part of our continued commitment to keep schools fully informed of progress within major projects we have developed a web site that schools are invited to visit to appraise themselves of their position within the NGfL Phase 5 project.

 

To remind you, the purpose of NGfL 5 is to ensure that all schools in Norfolk will reach the 2002 targets of pupil:PC ratios, as laid down by the DfES of 11:1 in the Primary sector and 7:1 in the Secondary and Special school sector.

 

Full instructions on how to access this site are detailed below, in summary it will show for your school:

 

1.      A brief high-level status report showing the milestone processes (copy attached).

2.      The result of the engineering survey, ie what PCs were found, what upgrades are required and what additional PC’s are required.

3.      Action taken to ensure any extra cabling and/or electrical requirements are met.

4.      What has been subsequently discussed and agreed with ICT Solutions Procurement team referencing orders, dates etc.

5.      Arrangements and dates for installation and/or upgrade of PCs, servers and printers.

6.      An indication of the training requirements.  As yet no dates have been arranged but within the next two weeks the ICT Solutions Help Desk will be contacting schools to make arrangements.

 

The web site also allows you to make comments on this process and indeed any other comments on ICT in general are most welcome so please use this facility.  You will receive a reply within five working days giving advice and/or any action we propose to take.

Continued/…..

The web site will continue to be developed with the following additional features:

 

1.   LAN drawing showing positions of existing and additional network points.

2.   Copies of all orders placed by ICT Solutions on behalf of the school.

3.      Specification of PC’s/Laptops/File servers and software titles belonging to the school.

4.      Specification of printers and other network devices.

 

To access the site you will need to visit the ICT Solutions website -http://ictsolutions.norfolk.gov.uk – and go to the index and click on ‘NGfL’. The user name and password are the same as for your email account ‘head@school.norfolk.sch.uk. Your ICT co-ordinator can similarly access the site by using their user name and password for the ‘ictc@’ account.

 

If you have any concerns regarding these processes you can contact Mike Cooke on 0845 303 3003 or email mike.cooke.edu@norfolk.gov.uk

 

Yours sincerely

Director of Education

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NGfL 5 PROCESSES

 

Process 1

The initial visit by Stella Mead or Mike Cooke whereby the overall NGfL vision is explained.  Ideas on networking, location of data points, PC, server and printer requirements are also discussed.  Two reports are produced, one that feeds into Process 2 summarising the PC and printer provision and one that feeds into Process 3 giving network and electrical requirements.

 

Process 2

With the report from Process 1 an engineer from ICT Solutions visits the school to assess the existing PCs and file server and makes recommendations on their suitability and any upgrades required.

 

Process 3

With the report from Process 1 the cabling contractor will make arrangements with the school to undertake a site survey from which a quotation for the work required is produced.  Once the quotation is accepted and an order placed, the contractor will again contact the school to arrange installation dates.  It is important to note that this process can be lengthy where on many occasions requotes to reduce costs have to be asked for.

 

The Process is not complete until the network has been installed as it is often essential before Process 5 can be implemented.

 

Process 4

From Process 2 the engineers recommendations are converted into quotations from PC suppliers.  Before orders are placed schools are asked to confirm that what is being asked for is correct.

 

Process 5

Following completion of both Process 3 & 4 an installation of PCs, etc is arranged with the school.  This will involve the PCs, etc being delivered to the school a few days beforehand.  This Process can take up to five days on site depending on the number of PCs to install.  Any upgrades or reimaging of existing PCs will also take place at this time.

 

Process 6

The final Process is training.  This is arranged from the ICT Solutions Helpdesk and for the Norfolk Toolbox solution consists of one or one and a half days on site.  For the RM solution it will involve two days in Oxfordshire and whilst the training is allowed for, travel and overnight accommodation unfortunately cannot be funded from this project.